01 October 2020 → 31 December 2022

Project Engagement & Consultation Phase

April → November 2020

Phase 1 - Basis of Design & Initial Investigation

Completed.

November 2020 → March 2021

Phase 2 - Detailed Design

March → June 2021

Phase 3 - Contracting and Procurement Activities

July 2021 → December 2022

Phase 4 - Construction Phase